FUEL CONTROL CENTER

One verified data chain from sounding to decision.

Recognizes the Excel template, applies vessel calibration, detects anomalies, tracks history and creates safe before/after bunkering plans.

FLEET SOUNDING STATUS

Select vessel

Latest saved sounding values
VESSEL TANK PLAN

Fuel Tank Arrangement and Live Quantities

VLSFO LSMGO 85% line Above 85%

Each tank shows fill %, m³, MT and temperature. Product colour fills the tank up to 85%; only the quantity above 85% is red. No.1 is forward and higher-numbered tanks progress aft. This operational view does not replace the approved General Arrangement or tank plan.

Total ROB--Latest verified mass
VLSFO / LSMGO--Product composition
Data Quality--Formula + source controls
Open Alerts--Requires review
LONG PERIOD

ROB Trend

TANK BARS

Fill Percentage by Tank

VLSFO LSMGO Limit
LATEST REPORT

Tank Results

--
TankProductm³MTFillMethod
ASSURANCE

Automatic Checks

AUTO RECOGNITION

Excel Sounding File

Upload an XLS, XLSX or XLK file. The system automatically recognizes the vessel, template, tanks and calculation method. Preview does not save data.

PREVIEW

Waiting for a file

--
Tank data, workbook/server variances and quality alerts appear here after preview.
SERVER CALCULATION

New Sounding Report

Previous tank values → temperature correction / VCF → MT
REPORT OUTPUT

Sounding Report PDF

Save the report to enable PDF output.
TankFuelSoundingVolume m³Temp °CDensity @15°C kg/m³Last confirmed supplyCorrected density kg/m³VCF / ModelCalculated MTFlag
LIVE BUNKERING CONTROL

Before / During / After Plan

85% safe target · 90% warning · 100% hard stop
REPORT OUTPUTS

Bunkering Plan PDF & Official Forms

Save the plan to enable PDF and Excel outputs.
BEFORE CONDITION
PLANNED TRANSFER→
AFTER CONDITION
CSM Official Form DataMSOF-09.1a and MSOF-09.1b fields. The approved templates are not redesigned.MSOF-09.1aMSOF-09.1b Rev 4
OPERATION TIMELINE

Capture each bunkering milestone

Pump Start begins the graph. Pump Stop closes it. Every time remains editable with an audit capture stamp.
TankFuelCapacity m³Before sound / ullageBefore m³Add m³After sound / ullageAfter m³Margin to 85% m³Tank statusDensity @15°CTemp °CLive sounding
LIVE FUEL LOADING CURVE

Pump Start - Tank Soundings - Pump Stop

Every tank sounding is plotted at its automatically captured time. Pump Start is time zero; Pump Stop fixes the final graph boundary.

Planned Measured Sounding
Enter planned m3 or add an intermediate sounding to build the live loading curve.
DOCUMENT PACK

BDN, Survey, Lab & Photos

Attach approved bunker documents and photographs. Large photos are automatically resized for secure storage and a compact report package.

Files selected now are uploaded after the plan and sounding timeline are saved.
No documents selected.
OFFICIAL SAFETY CONTROL

MSOF-09.1b Bunkering Safety Checklist

Plan, tank, vessel, port and rate data fill automatically. Safety confirmations require an authorised user selection and are never inferred.

0%0 / 50 confirmed
Six rounds per side are transferred to the official PDF.
BUNKERING FIELD CALCULATOR

Quick Sounding

Select the vessel above, enter trim and the tanks measured. The existing vessel calibration and temperature correction calculate current MT and fill percentage without requiring a Bunkering Plan.

CALCULATION ONLY · NOT SAVED

Heel is assumed to be 0°. Density is entered at 15°C in kg/m³. Only tanks with complete readings are included in the measured-tank total; this is not the vessel's full ROB unless all fuel tanks are measured.

Measured tanks0 / 0 Total measured fuel— Total measured volume— Measured capacity filled—
Enter trim and at least one complete tank reading.
MOBILE FIELD ENTRY

Rapid Bunker Operation

Enter the current sounding. Tank volume, received fuel, remaining delivery and fill percentage are calculated from the selected Bunkering Plan and its previous sounding report.

LIVE
Select a vessel with a saved Bunkering Plan.
Waiting for soundingValues above 85% trigger a red tank alarm.
AUDIT TRAIL

Sounding Reports

DateVesselSourceROB MTQualityAlertsFiles
BUNKERING

Saved Plans and Official Forms

DateVesselPlanRevisionSupply MTAfter MTAlertsActions
TANK SUPPLY HISTORY

Enter confirmed supply